One of the engineers identifies the key design software has a | Project Management B.2 (PrMaB2)

One of the engineers identifies the key design software has a problem and willnot be operational for 2 days.As the risk manager you had already considered that there was a chance something may happen with the software since it was new. Now you must first:
Anonymous Quiz
16%
Log the risk.
53%
Review the risk response plan and risk register
5%
Use the management reserve
26%
Submit a change request and process through integrated change control