KALYANI STEEL : Company has commissioned Coke Making Facility | STOCKMARKET INFOMANIA

KALYANI STEEL : Company has commissioned Coke Making Facility and partially commissioned Waste Heat Recovery (WHR) based Captive Power Plant, adjacent to its steel plant situated at Village Ginigera, Hospet Road, Koppal
District, Karnataka

Company had planned to set up a 200,000 TPA Non-recovery / Heat recovery, stamp charged Coke Oven with Modified wet Quenching of hot coke and 17-18 MW captive power plant to be operated utilizing waste heat energy of flue gas generated from Coke Oven. The electrical power so produced shall be used for captive consumption and the surplus, if any, will be sold to external agencies. The Broad
Specifications were as follows :

Coke Oven

o Annual capacity (Dry coke) – 0.2 MT

o No. of Ovens – 72 (Divided in two batteries of 36 ovens each)

Heat Recovery Captive Power Plant

o Power generation capacity – 17-18 MW

o Generation voltage – 11KV