Further Simplified Claim Process for Prolongation Costs in Public Sector Construction Contracts due to COVID-19 Events

MOF and BCA have introduced a further simplified approach for non-manpower related prolongation cost claims to public sector construction contracts with contract value above $100million.

Government agencies will provide a base $100,000 for every month of certified delay due to COVID-19 as payment for cost sharing of non-manpower related cost increases under Part 8B of COTMA. No substantiation from contractors is required to accompany the claim for this base $100,000.

This is in addition to BCA’s circular dated 27 Apr 2021 on the simplified approach for non-manpower related prolongation cost claims, which provides a base 0.1% of awarded contract sum for every month of certified delay, for eligible contracts with awarded contract sum up to $100 million.

For more details, visit:
Circular
https://go.gov.sg/bca-tlg-circular-further-simplified-claim-process